Record what a supplier sells and at what price
Each pairing of a supplier and an item is one row: who sells it, at what price, since when, in what minimum quantity and how fast. A new purchase order reads these rows to fill in the price for you.
Add a row from the supplier
Section titled “Add a row from the supplier”- Open Production → Suppliers and open the supplier.
- Go to Products purchased.
- Click Add item.
- Choose the Item kind (Material or Product) and the Item.
- Enter the Quoted price, the Currency and the Quotation date. The date is required: a price with no date is a number nobody can judge.
- Optionally add the Minimum order quantity, Lead time, days, Supplier’s item code (the code on their invoice) and Link to the item on their site. Only
httpandhttpsaddresses are accepted. - If this is who you normally buy from, turn on Our main supplier for this item.
- If the supplier gives a better price for more units, fill in Price by quantity (see below).
- Click Save.
You can also start from the material: open it in Production → Materials, find Suppliers and click Add supplier.
Record a price by quantity
Section titled “Record a price by quantity”Price by quantity is a ladder. Click Add a tier for each step and enter its From quantity and Unit price. From each From quantity up, the unit price is the Unit price you gave it; below the first step the Quoted price applies. Tiers are kept in order of quantity, so you can add them in any order.
The ladder is part of the quote. A purchase order line does not pick a tier for you: it is filled in from the Quoted price, so for a large order enter the tier price on the line yourself.
What the main supplier does
Section titled “What the main supplier does”Only one supplier per item can be the main one. Turning it on moves the mark from whoever held it. When you add that item to a purchase order, Keelvy offers the main supplier and fills in the price from their row, marked “quoted” with the date. It leaves the price blank when the quote is in a different currency from the order, and does nothing if the supplier is archived.
Lead time feeds the reorder plan
Section titled “Lead time feeds the reorder plan”The Lead time, days on a row is what the replenishment plan uses to work out the date to order by. It reads the main supplier’s lead time first and, if that row has none, the shortest lead time recorded for the material. The days the supplier’s goods then spend on the road come from Delivery time (days) on the supplier’s card.
Bought but never quoted
Section titled “Bought but never quoted”The catalog on the supplier’s card has a Show filter: Everything, Quoted, Bought, never quoted and Ever bought. “Bought, never quoted” lists items you have received from them but never recorded a quote for. Use Record a quotation on a row to fix that.
Order several items at once
Section titled “Order several items at once”Tick items in the catalog and click Create purchase order to raise one order for everything selected, or use Order from this supplier on a single row.
Remove a row
Section titled “Remove a row”Remove offering archives the row. The item stops being recommended for that supplier, and the purchase history stays.