Plan what to reorder and when

The materials list tells you what you have. Production → Replenishment plan tells you what you will not have, by when to act, and how much to order.

The plan walks forward day by day from today. For each material it starts from what is on the shelf, adds what is still coming on open purchase orders, and takes away what unfinished production orders will draw.

Choose the Horizon. For each material the table shows:

  • On hand and Minimum.
  • Days of stock: what is available divided by what leaves per day, with Critical when it runs out before a reorder could arrive and Low when it is inside the safety buffer.
  • Minimum breached: the day stock falls below the minimum.
  • Runs out: the day it reaches zero.
  • Lead time: how many days a supplier needs, with the supplier’s name.
  • Order by: the last day to order so the material arrives in time. An order date already past reads Overdue.
  • Below minimum by and Suggested order: how far under the minimum it falls, and how much to order.

By default only materials that need a decision are listed. Use Show every material to see them all, and Show only what needs a decision to go back.

The suggested quantity is sized from what actually left stock, not from a guess. Three settings shape it:

  • Average use over: the last 30, 60 or 90 days.
  • Cover: how many days of use a suggested order should last after it arrives. Move it and the suggestions recalculate at once.
  • Safety buffer: days of average use kept as margin on top of lead time and delivery. This is the workspace default and anyone who manages settings can change it. A material can set its own on its card, under Safety buffer (days).

Click Why? beside a suggestion to read the sum: the daily use, the days the order has to last (the supplier’s lead time, the delivery time and your cover), the buffer, then what is needed minus what is in stock and already on order. The line also says when the quantity was raised to the supplier’s minimum order or rounded up to whole packs. A material already covered says so, and a note under the suggestion shows how much is already waiting in draft purchase orders.

A note beside a material says why its answer is less certain:

  • No lead time: no supplier row for this material records a lead time, so there is no order-by date. Add one on the supplier’s price row. See Record what a supplier sells and at what price. The suggested order counts it as 0 days.
  • No minimum: the material keeps no buffer, so only the day it runs out is reported.
  • Unit not converted: an inbound purchase line is in a unit that cannot be converted to the material’s own, so its quantity is counted as written.

The dates come from production orders, not from sales orders. A confirmed sales order with no production order behind it produces no material demand here, because turning an order into a plan means choosing batch sizes, which site, and whether to make or buy. The chain is: confirm the order, plan the production, then read this screen.

The plan reads specifications, so you need permission to see them.

Select materials in Production → Materials and choose Create purchase order, or let a scenario draft the orders. See Order what is running low.